This set of Civil Engineering Multiple Choice Questions & Answers (MCQs) focuses on “ Construction Planning & Management ”. These Mcqs are chosen from a collection of most authoritative and best reference books on Civil Engineering. Our aim is to prepare an individual for competitive exams like NTS, GAT, ECAT, University and College entrance exams, Jobs and interviews. One should practice our MCQS to assimilate Construction Planning and Management comprehensively.

  1. Home
  2. »
  3. Engineering
  4. »
  5. Civil Engineering Mcqs
  6. »
  7. Construction Planning and Management Mcqs
  8. »
  9. Page 6

76.
Select the incorrect statement?

Start float and finish float are always equal

Total float can be either start float or finish float

Start float and finish float need not be equal

Start float and finish float are the differences between activity times and not event times

77.
Select the incorrect statement?

A critical path always begins at the very first event

A critical path always terminates at the last event

Critical activities control the project duration

Critical activity is the one for which free float is zero